OpManager provides you the option to suppress the alarms of the devices for a pre-defined time interval. This option will be useful in cases where the devices are under maintenance or some known issues exist with them.
Group alarm suppression allows you to suppress alarms for all devices within a specific group. This is useful when you want to avoid receiving alarms during maintenance or while performing updates on an entire group of devices. Refer to the Configuration methods for Alarm suppression section for detailed steps.
Category alarm suppression lets you suppress alarms for devices belonging to a specific category, such as WLAN devices, UCS servers, or printers. This feature is beneficial when certain categories of devices require maintenance or upgrades. Refer to this section for detailed steps.
Inventory
- Navigate to Inventory → Devices.
- Select a device, click the three-dot icon on the top right, and choose Suppress Alarm.
- Set the required suppression duration.
- The suppression icon appears in the Suppressed column for the respective device.
- In the same suppression window, users can view the configured suppressions.
- Delete individual entries or use Delete All to remove all suppressions for that device.
Device snapshot page
- Open the device’s snapshot page.
- Click the menu icon on the top right and select Suppress Alarm.
- Choose the suppression period.
- The suppression icon is displayed near the device status, within the Recent Alarms tab, and on the Alarms icon.
- From the suppression details on the snapshot page, users can delete individual suppressions or select Delete All.
Note:
- When a device has multiple alarm suppressions configured, i.e., via categories and groups, using the Delete All option from the Suppression window will only delete device-specific alarm suppressions. Category or group-based suppressions will remain unaffected. To delete category or group-based suppressions, use the Quick Configuration Wizard (QCW).
Similarly, when multiple suppressions are configured for a device, the longer suppression will automatically take effect. For example, if suppressions are set for 8 hours and 1 day, the 1-day suppression will be applied automatically.
Inventory
- Navigate to Inventory → Interfaces.
- Select an interface, click the three-dot icon on the top right, and choose Suppress Alarm.
- Set the suppression duration.
- The suppression icon appears near the interface name in the interface list.
- In the same suppression window, users can view and delete individual suppressions or select Delete All for that interface.
Interface snapshot page
- Open the interface’s snapshot page.
- Click the menu icon and select Suppress Alarm.
- Define the suppression period.
- The suppression icon is displayed near the interface summary.
- From the suppression details, users can delete individual entries or choose Delete All.
Device Snapshot Page (Monitors Tab)
- Open the device snapshot and navigate to the Monitors tab.
- Select one or more monitors, then click the menu icon and choose Suppress Alarm.
- Set the required suppression duration.
- The suppression icon appears next to the monitor name in the Monitors tab and is also visible in both graph and forecast views.
- From the suppression details in the Monitors tab, users have the ability to delete individual suppressions or select Delete All.
Users can apply filters to narrow down the devices for which alarm suppression is applied. There are four available filter options:
- Devices: Discovered devices can be further refined based on Business View, Groups, or Virtual Servers. Additionally, devices can be filtered by their category.
- Category: The category of the device (e.g., WLAN, UCS, Printer, etc.).
- Group: The groups created in OpManager.
- Global URL: The monitored URLs in OpManager. To view the list of monitored Global URLs, navigate to Settings → Monitoring → URL Monitors.
Quick Configuration Wizard (QCW)
- Open QCW and select Configure.
- Choose the appropriate filter type—Category, Group, or URL—depending on the suppression you wish to apply.
- Apply the required suppression settings.
- Use the Remove option in QCW to clear all suppressions applied for the chosen filter type.
Workflow
- Navigate to Workflow → New Workflow.
- Drag and drop the Suppress Alarm action from the OpManager dropdown.
- Select the appropriate suppression type (such as Group, if applying to groups) and follow the configuration steps to set up the suppression.
- Users can remove the configured suppressions by setting the suppression time period to Never within the workflow configuration.
Device downtime schedules
Configuration:
- Navigate to Settings → Configuration → Device Downtime Schedules.
- Select Suppress Alarm, set the frequency, and use the filter to select the required devices, groups, or URLs.
- Click Save.
- Go to the Device Downtime Schedules page and click the delete icon to remove the alarm suppression.
Note:
- Suppression through Device Downtime Schedules can only be configured on the Standard and Probe servers. Currently, this configuration is not supported from the Central server.
- Alarms suppressed via Device Downtime Schedules will not be listed in the Alarm Suppression window. These suppressed alarms can only be viewed on the Device Downtime Scheduler List page.
Supported monitors list for Alarm Suppression,
Given below are the list of monitors for which Alarm suppression is supported,
- Performance Monitors
- URL Monitors
- Service Monitors
- Process Monitors
- MSSQL Service Monitors
- AD Service Monitors
- Exchange Service Monitors
- MSSQL Monitors
- AD Monitors
- Exchange Monitors
- Windows Service Monitors
- File Monitors
- Folder Monitors
- EventLog Monitors
- Script Monitors